Modernización de regadíos tradicionales del Júcar. Fase I. Balsa de suministro en alta en la Acequia Real de Escalona

Descripción de las obrasEstado:

Esta obra forma parte de la Modernización de regadíos de la Real Acequia de Escalona y tiene como objeto el ahorro de recursos como consecuencia del aumento de las eficiencias en el uso el agua y la mejora de la calidad de las masas de agua como consecuencia de una menor aplicación de fertilizantes al cambiar el método de aplicación del agua en parcela y pasar a sistemas de riego tecnificado y la reducción de las necesidades de herbicidas.

INSTALACIONES:

Maintenance and operation of the Turia - Sagunto pipeline

Descripción de las obrasEstado:

This action consists of the Maintenance and Operation of the facilities already built connecting the Canal Júcar-Turia with the city of Sagunto. Its purpose is to optimise the use of water and its proper exploitation

STATE OF THE ACTION:
The works are in operation.

INSTALACIONES:

Rabasa-Fenollar-Amadorio pipeline

Descripción de las obrasEstado:

Maintenance of facilities constructed from Fenollar to Amadorio to optimise the use of water and its proper exploitation.

STATE OF THE ACTION:
The works are in operation.

INSTALACIONES:

Elevation of waters from Rabasa to Fenollar

Descripción de las obrasEstado:

Pipeline that links the deposits of Rabasa and Fenollar and their corresponding impulse. This work aims to ensure the supply of the regions of L'Alicanti and Marina Baja, where an overexploitation of aquifers is occurring.

STATE OF THE ACTION:
The works are in operation.

INSTALACIONES:

Flood prevention in the barranco Benimodo

Descripción de las obrasEstado:

The purpose of this action is to prevent uncontrolled overflow from the Barrabco Benimodo on a 7km long stretch between the junction of the latter with the Barranco de la Parra and the A-7, so that an adequate level of protection against the risk of floods is reached in the neighbouring towns of Carlet, Benimodo, L'Alcudia, Guadassuar and Massalaves, thereby avoiding economic and social impacts that are caused by flooding.

STATE OF THE ACTION:
Work received and delivered.

INSTALACIONES:

Conditioning of lower Serpis as consequence of flood prevention in the middle basin

Descripción de las obrasEstado:

The works are concentrated in the town of Gandia within the boundaries of the so called "Protected Landscape of the Serpis". There will be different actions such as protective walls, creating a channel for low water, actions on the old bridge of Oliva, pumping water for recycling and cleaning and revegetation treatments as well as conditioning of paths, all of which are being studied.

STATE OF THE ACTION:

Works that have been met and received.

INSTALACIONES:

Infrastructures for flood prevention in the middle basin

Descripción de las obrasEstado:

The purpose pursued by the action is to increase the level of protection against floods in the middle basin of the river Serpis. To achieve this the construction of a dam in the town of Terrateig is being studied, together with building defences against erosion and flooding in various parts of the whole basin and diverting part of the flow from the Barranco de Piles to the river Serpis, all complemented with environmental mitigation measures associated with the works included in the action.

STATE OF THE ACTION:
Work underway.

INSTALACIONES:

Lamination and improved drainage in the basin of Rambla Gallinera

Descripción de las obrasEstado:

The purpose of the action is the protection against floods in the basin of the rambla Gallinera and Alfadalí ravine, carrying out the provisions of the Director Plan of Defence against Floods in the region of La Safor.

INSTALACIONES:

Major repairs and automation of the main channel of Campo del Turia (Valencia). Division 1 and 2

Descripción de las obrasEstado:

The purpose of this action is to ensure that the channel properly provides the service for which it was designed, that is to transport water from the river Turia, from Benagéber Reservoir, to the Campo del Turia, for irrigation. Currently this service cannot be provided with sufficient guarantees due to numerous structural problems and deficiencies in the control elements.

INSTALACIONES:

Modernisation of Júcar-Turia channel (Valencia)

Descripción de las obrasEstado:

The main object of this action is to eliminate the vulnerability of supply of Valencia which is caused by the fact of being supplied through a free surface pipeline. To avoid this and to optimise the management of resources, the transport of flows for supply using a pressure pipe are planned to be encased.

STATE OF THE ACTION:
Under study phase for alternatives.

INSTALACIONES:

Páginas