Elimination of chemical contamination from the Flix reservoir 1st stage

Elimination of chemical contamination from the Flix reservoir 1st stage
Scope of action: Cuenca Hidrográfica del Ebro
Total investments: 194,000,000 €

Description of worksState: Works in progress

Flix Reservoir retains a lot of sludge in its basin that originated from historical discharges from the chemical activity and changes in the fluvial dynamics of the river through the construction of the Mequinensa, Ribarroja and Flix dams. The main objective of the action is to reduce the inherent risk in the accumulation of contaminated waste in the Flix reservoir by its disposal. For this planning has been carried out to extract, process, transport and dispose the waste accumulated in the basin into a controlled deposit.

STATE OF THE ACTION:

The work is in progress.

INSTALLATIONS: