Carboneras desalination plant

Descripción de las obrasEstado:

The infrastructure consists of a desalination plant for seawater with treatment capacity of 120,000 m3/day, and a pipeline to supply water to the town of Carboneras and Agua Amarga (Pedanía Nijar). Guaranteed resources are generated with the action for the supply and to East Almería and for irrigation to Campo de Nijar. These resources are then distributed with the infrastructures included in the proceedings "1.2.c Interconnection Carboneras- Almanzora" and "6.2.c Connection Almanzora -West Almería Phase I".

STATE OF THE ACTION:

INSTALACIONES:

Project for additional works of the Mutxamel desalination plant towns of San Juan, Alicante and San Vicente del Raspeig

Descripción de las obrasEstado:

The works included in this action correspond to regulation and distribution works needed to supply the towns of San Juan, Alicante and San Vicente de Raspeig with desalinated water from the desalination plant of Mutxamell. The construction of three regulation tanks have been planned for this with storage capacity for 33,000 m3, 4 drives and 17 km of pipelines.

STATE OF THE ACTION:
The initiative is divided into two project divisions:

- The works of division No. 1 are in progress.

-The works of division No.2 are pending tender.

INSTALACIONES:

Reinforcement project for the supply networks of the municipalities of Mutxamel and Campello

Descripción de las obrasEstado:

The infrastructures included in this action include regulation and distribution works needed to supply drinking water from new desalination plant of Mutxamel to the towns of Campello and Mutxamell (Alicante) and connect the system with the Rabasa-Amadorio pipeline which currently is in operation (See the data sheet of the action Rabasa-Fenollar-Amadorio pipeline). The works included in this action can be summarised in the construction of 3 tanks with a total volume of 16,000 m3, 4 pumping stations and 26 km of pipelines.

STATE OF THE ACTION:
Works pending award.

INSTALACIONES:

Desalination and additional works for Marina Baja. Muxamel

Descripción de las obrasEstado:

The aim of this action is the provision of new resources to ensure supply of the L'ALACANTI area. This new source of supply frees underground resources of overexploited aquifers and allows, in emergency situations, to support the supply of the Marina Baja region. To achieve this goal a new seawater desalination plant is being built in the town of Mutxamel with a production capacity of 50,000 m3/day, extendible to 80,000 m3/day.

STATE OF THE ACTION:

Works received.

INSTALACIONES:

Desalination plant of Sagunto, Valencia

Descripción de las obrasEstado:

The purpose of the action is to cover part of the water deficit that is expected in the short to medium term as a result of population growth and industrial expansion, of the town of Sagunto and the rest of the district of Camp de Morvedre. To achieve this goal a new desalination plant has been designed with a production capacity of 22,900 m3/day, which is used for domestic and industrial use. The plant is located next to the new combined cycle power plant of the company Unión Fenosa Generación in the port of Sagunto.

INSTALACIONES:

Water allocation system from Cerro Colorado reservoir to the Guadalentin valley

Descripción de las obrasEstado:

The project involves construction of a pipeline that will feed desalinated water from Águilas desalination plant to the Irrigation Communities of Puerto Lumbreras and Lorca, established along the Valle del Alto Guadalentín. The source of the pipeline is established in the Cerro Colorado reservoir, which forms part of the actions of the Águilas/Guadalentín desalination plant.

Works are underway

INSTALACIONES:

Supply project to Pulpi

Descripción de las obrasEstado:

The purpose of the action is to provide the towns of the coastal area of Pulpí with a pipeline that will cover the supply requirements planned in the future with resources from the desalination plant of Águilas/Guadalentín. The new pipeline, with capacity to supply a flow of 2 hm3/year will complement the existing one managed by GALASA, so that between the two they can meet the daily consumption forecast for the days of maximum occupancy.

The works are pending tender.

INSTALACIONES:

Distribution to the irrigation community of Puerto Lumbreras

Descripción de las obrasEstado:

This purpose of this action is aimed at the link between the distribution network of the Águilas desalination plant and the irrigation network of the Irrigation Community of Puerto Lumbreras, in order to properly manage the new water resources granted.

As a solution for this link, the construction of a reservoir with a 40,000m3 intake capacity is planned, where the water will pour from Cerro Colorado using gravity, and from this reservoir an impulse to take it towards Peñas Blancas, to the existing reservoirs of the Irrigation Community.

INSTALACIONES:

Cerro Blanco pipeline to the water treatment plant of El Atabal

Descripción de las obrasEstado:

To improve the current high level supply network in the city of Málaga, which currently runs through a system of open channeling together with the irrigation, a water catchment is made use of in the Azud de Aljaima, in the channel of the river Guadalhorce, remodeling existing pumping facilities, and a 21 kilometer pipeline from the catchment to the desalination plant of El Atabal.

INSTALACIONES:

Mijas and Manilva tertiary WWTPs

Descripción de las obrasEstado:

The aim of the action is to incorporate the waste water treatment plants of Cala Mijas and Manilva to the tertiary treatments needed to regenerate the purified water, so that water quality being supplied to the golf courses and green areas is improved. The action provides for the distribution of reclaimed water to the golf courses in line with Article 4 of Decree 240/2005 of 2 November, of the Junta de Andalucía, which governs the exceptional measures during drought in various municipalities in Málaga, including those of the western Costa del Sol.

INSTALACIONES:

Páginas